Preliminary Bid Packages & Procurement Schedule
Bid Package 1: MEP - Design Assist
March 2010 (Use Schematic Design Documents)
| Mechanical/Plumbing/Med Gas/Controls | $153,600,000 |
| Electrical/fire Alarm/Lighting Controls | $82,400,000 |
| Fire Protection | $6,000,000 |
| Low Voltage Systems | $47,500,000 |
| Subtotal | $289,500,000 |
Bid Package 2: Foundations
August 2010 (Use Bid Package 2 Documents)
| Excavation | $5,300,000 |
| Shoring | $60,000 |
| Drilled Piers | $2,700,000 |
| Formwork | $1,200,000 |
| Reinforcing Steel | $3,900,000 |
| Concrete | $3,300,000 |
| Concrete Place & Finish | $290,000 |
| Hoisting & Equipment | $9,800,000 |
| Waterproofing | $500,000 |
| Subtotal | $27,050,000 |
Bid Package 3: Superstructure
November 2010 (Use Bid Package 3 Documents)
| Formwork | $15,600,000 |
| Reinforcing Steel | $21,400,000 |
| Concrete | $17,100,000 |
| Concrete Place and Finish | $2,100,000 |
| Subtotal | $56,200,000 |
Bid Package 4: Design Development
November 2010 (Use Design Development Documents)
| Buy | |
| Exterior Glass/Glazing | $43,300,000 |
| Elevators | $20,400,000 |
| Misc. Steel (Stairs, etc.) | $9,600,000 |
| Price | |
| Remainder of Project (See BP-5) | |
| Subtotal | $73,300,000 |
Bid Package 5: Remainder of Project
April 2011 (Use 100% Construction Documents)
| Paving | $5,000,000 |
| Landscape/Irrigation | $4,900,000 |
| Site Utilities | $2,900,000 |
| Architectural Precast | $900,000 |
| Masonry | $2,600,000 |
| Exterior Stone | $2,500,000 |
| Remaining Misc. Steel | $3,200,000 |
| Ornamental Metals | $400,000 |
| Canopies | $3,100,000 |
| Finish Carpentry/Millwork | $24,400,000 |
| Waterproofing | $3,500,000 |
| Roofing | $4,800,000 |
| Metal Panels | $6,400,000 |
| Sprayed Materials | $100,000 |
| Doors/Frames/Hardware | $11,800,000 |
| Overhead Doors | $200,000 |
| Plaster | $800,000 |
| Interior Glass/Glazing | $4,600,000 |
| Drywall/Acoustical | $35,300,000 |
| Tile/Interior Stone | $5,700,000 |
| Terrazzo | $2,500,000 |
| Flooring | $13,800,000 |
| Paint/Wall Covering | $6,600,000 |
| Specialties | $5,300,000 |
| Operable Partitions | $20,000 |
| Access Flooring | $100,000 |
| OFCI Equipment | $1,000,000 |
| Building Maintenance Equip. | $1,200,000 |
| Food Service | $4,000,000 |
| Medical Equipment | $10,000 |
| Parking Equipment | $200,000 |
| Radiation Protection | $600,000 |
| Water Features | $2,500,000 |
| Helistops | $1,100,000 |
| Chutes | $300,000 |
| Pneumatic Tube System | $3,000,000 |
| Subtotal | $165,330,000 |