Preliminary Bid Packages & Procurement Schedule

Bid Package 1:  MEP - Design Assist

March 2010 (Use Schematic Design Documents)

Mechanical/Plumbing/Med Gas/Controls $153,600,000
Electrical/fire Alarm/Lighting Controls $82,400,000
Fire Protection $6,000,000
Low Voltage Systems $47,500,000
Subtotal $289,500,000

Bid Package 2:  Foundations

August 2010 (Use Bid Package 2 Documents)

Excavation $5,300,000
Shoring $60,000
Drilled Piers $2,700,000
Formwork $1,200,000
Reinforcing Steel $3,900,000
Concrete $3,300,000
Concrete Place & Finish $290,000
Hoisting & Equipment $9,800,000
Waterproofing $500,000
Subtotal $27,050,000

Bid Package 3:  Superstructure

November 2010 (Use Bid Package 3 Documents)

Formwork $15,600,000
Reinforcing Steel $21,400,000
Concrete $17,100,000
Concrete Place and Finish $2,100,000
Subtotal $56,200,000

Bid Package 4:  Design Development

November 2010 (Use Design Development Documents)

Buy  
Exterior Glass/Glazing $43,300,000
Elevators $20,400,000
Misc. Steel (Stairs, etc.) $9,600,000
Price  
Remainder of Project (See BP-5)  
Subtotal $73,300,000

Bid Package 5:  Remainder of Project

April 2011 (Use 100% Construction Documents)

Paving $5,000,000
Landscape/Irrigation $4,900,000
Site Utilities $2,900,000
Architectural Precast $900,000
Masonry $2,600,000
Exterior Stone $2,500,000
Remaining Misc. Steel $3,200,000
Ornamental Metals $400,000
Canopies $3,100,000
Finish Carpentry/Millwork $24,400,000
Waterproofing $3,500,000
Roofing $4,800,000
Metal Panels $6,400,000
Sprayed Materials $100,000
Doors/Frames/Hardware $11,800,000
Overhead Doors $200,000
Plaster $800,000
Interior Glass/Glazing $4,600,000
Drywall/Acoustical $35,300,000
Tile/Interior Stone $5,700,000
Terrazzo $2,500,000
Flooring $13,800,000
Paint/Wall Covering $6,600,000
Specialties $5,300,000
Operable Partitions $20,000
Access Flooring $100,000
OFCI Equipment $1,000,000
Building Maintenance Equip. $1,200,000
Food Service $4,000,000
Medical Equipment $10,000
Parking Equipment $200,000
Radiation Protection $600,000
Water Features $2,500,000
Helistops $1,100,000
Chutes $300,000
Pneumatic Tube System $3,000,000
Subtotal $165,330,000